Solar & Storage
Cass County Solar
Beardstown, Illinois
Solar & Storage
Cass County Solar
Beardstown, Illinois
Kiewit provided engineering, procurement and construction services for a 195 MW solar facility and a 34.5/138kV collector substation. The 1,100-acre site scope included site clearing, access road construction, alternating and direct current electrical work, post and racking installation, module placement, inverter installation, system startup, commissioning and performance testing. Crews installed 329,344 Risen 590/595-watt solar modules and 5,416 GameChange racking systems. Additional work included installation of major equipment, conduit, grounding, power and control cabling, as well as bus and jumper components.