Raw Water Pump Station and Pipeline from Union Hills Water Treatment Plant to Cave Creek Water Reclamation Plant - Phoenix, AZ
This project provided the ability to supply untreated Central Arizona Project (CAP) water from the Union Hills Water Treatment Plant to the Cave Creek Water Reclamation Plant, utilizing approximately 5,000 LF of 24-inch HDPE pipe. The project included the installation of a 10 MGD booster pump station, screening facilities, chemical and electrical system updates, and a 1,300 LF horizontal directional drill. Other aspects of the project included site restorations, landscaping, paving activities, and mechanical filters at the booster station to control biological growth such as quagga mussels.