Creighton University is the only university in the nation with a soccer-only stadium. The university wanted a facility as top-notch as its program, which is NCAA-ranked and an important component of the school's culture. In August 2002, the $12 million project was initiated and became part of Creighton University's master plan to expand its campus infrastructure.
Early involvement and collaboration among the entire project team resulted in cost and schedule savings. Team meetings between the designers and Kiewit Construction Company, a subsidiary of Kiewit Corporation, determined the availability and cost-effectiveness of long-lead items. The stadium was completed November 2004 - just in time for the Creighton Bluejays to host the Missouri Valley Conference championship tournament.